Project Name-


Construction of 383.02m long & Pre-stressed Concrete Girder & Steeltruss Bridge (2nd Dholeshwari Bridge) on Cast in-situ bored pile foundation at 18th k.m. of Dhaka-Khulna Highway under Munshigonj Road Division.
 

Client-

Roads & Highways Department
Ministry of Communication
Government of Bangladesh

Project Cost in Million-

BDT 331.60
(Equivalent to USD) 7.99

Salient Feature-

• Pre-stressed concrete girder & steel truss and RCC bridge(composite construction)
• Approach road
• earth work, flexible pavement, asphalt concrete work
• River training & bank protection work
• Piling work:
i) Land based pile (1000 mm dia 30m long cast-in-
situ bored pile)
ii) Water based pile by barge mounted rig (1000 mm
dia 35 m long cast-in-situ bored pile)
iii) Total nos. of pile 118 Nos.
• Temporary jetty for pre-stressing work
• 2X88m steel truss erection
• Length of bridge 383.02m
• Width10m (2 lane)
• Nos. of span 8 Nos.
• Nos. of PC girder 30 Nos.
• Nos. of pier 7 Nos.
• Abutment 2 Nos. & counterfort type